Channel

Duke Energy Makes Data Centers Pay Upfront for Grid Costs

Duke Energy Makes Data Centers Pay Upfront for Grid Costs

CHARLOTTE, N.C. — Duke Energy and stakeholders have reached an agreement that further protects existing customers from costs to serve data centers and other large-load customers in North Carolina.

Duke Energy proactively implemented substantial customer protections in 2024 to ensure that large-load customers pay the costs to serve them. The agreement memorializes and enhances those protections.

These changes are reflected in a new settlement between the company’s two North Carolina utilities – Duke Energy Carolinas and Duke Energy Progress – and North Carolina Public Staff, the agency representing utility customers. Other parties to the agreement include Amazon, Google, Meta, Microsoft, Carolina Industrial Group for Fair Utility Rates and the U.S. Department of Defense.

“It’s simple – data centers will pay upfront for all costs to connect to the grid,” said Kendal Bowman, Duke Energy’s North Carolina president. “We’re shielding other customers from these costs in a way that protects reliability and ensures everyone benefits from the economic growth coming to North Carolina.”

Agreement summary:

  • Nonrefundable, upfront payment for electric grid facilities serving only that customer, such as a substation to connect to the grid.
  • Upfront deposits and security guarantees for grid upgrades that serve all customers, such as transmission lines.
  • New large-load customers, including new data centers, must take service under a High Load Factor rate schedule – a separate rate established for large loads.

Duke Energy had previously required data centers and other large loads (100 megawatts or more) to agree to contract terms that protect other customers from such costs. If approved by state regulators, this new agreement would apply to all large-load customers (50 megawatts or more with 80% load factor) that sign an electric service agreement (ESA) in North Carolina after June 1, 2026. ESAs signed prior to June 1 contain a full suite of similar customer protections.

In July, Duke Energy announced its Customer Protection Plus framework, outlining how data center growth will result in billions of dollars of future customer benefits, saving money for existing customers. This agreement adds to that framework in a way that specifically addresses issues raised by North Carolina regulators and customers. Learn more about Duke Energy’s approach to data centers at duke-energy.com/DataCenters.

What’s next: The agreement is subject to approval by the North Carolina Utilities Commission – a decision is expected by mid-November.

Duke Energy Carolinas serves about 2.3 million households and businesses in central and western North Carolina, including Charlotte, Durham and the Triad, while Duke Energy Progress serves about 1.6 million customers in central and eastern North Carolina and in the Asheville region. The two will combine into a single utility on Jan. 1, 2027.

Tagged with , ,

Comment on the story

Your email address will not be published. Required fields are marked *